Last updated: November 2026. Written by Marco, owner of Genpro LLC, a licensed general contractor building ADUs in Seattle and on the Eastside.
Most detached ADUs (DADUs) in Seattle and Bellevue land somewhere between the mid $100,000s and the high $300,000s, turnkey, in 2026. A small studio sits at the low end. A full two- or three-bedroom unit sits at the top.
Where your project falls depends mostly on two things: the size of the unit and the lot it sits on. A steep slope, soft soil or a long sewer run can add tens of thousands of dollars. That's why we built the Genpro ADU planner. It gives you a ballpark for your own project in about two minutes.
How long does it take? Plan on roughly a year to a year and a half from first sketch to move-in. The city permit alone usually takes about 5 to 7 months in Seattle right now.
How much does an ADU cost by size?
Rough turnkey ballparks for 2026, on a normal, buildable lot:
• Studio (around 450 SF): starts in the mid $100,000s
• One bedroom (around 650 SF): usually in the low to mid $200,000s
• Two bedroom (up to 1,000 SF, the Seattle maximum on most lots): usually in the $300,000s
• Three bedroom (around 1,200 SF, larger Bellevue lots): usually in the $400,000s
Turnkey means design, permits, foundation, construction, utilities and finishes, ready to move into or rent. Smaller units cost more per square foot, because a kitchen, a bathroom and the utility hookups cost about the same no matter how small the unit is.
These are starting points, not quotes. For a number based on your size, finish level and lot, use the ADU planner.
What fees should you expect?
Beyond the permit itself, plan for a few utility and connection charges. The one most owners hear about last is the King County sewer capacity charge. For a new DADU it works out to roughly $8,000 in total, billed monthly over 15 years, and it applies in both Seattle and Bellevue. You can pay it off early at a discount.
Other costs to expect, all depending on your lot:
• Building permit and plan review fees
• A new electrical service or meter
• A water service upgrade, if the existing line is too small
Sources: King County capacity charge, Seattle sewer use form.
What makes some lots so much more expensive?
The lot, not the building, causes most of the big surprises. Five things to check before you trust any price:
• Steep slopes. Seattle maps many hillsides as Environmentally Critical Areas. Building there usually means a soils report, an engineered foundation and extra review time.
• Peat and soft soil. Parts of north Seattle sit on peat. The foundation then needs piles driven down to firm ground.
• Sewer distance and depth. A long run from the back of the lot adds cost by the foot. If the ADU sits lower than the street sewer, it may also need a pump.
• Access. If there's no side yard wide enough for equipment, materials get hand-carried or lifted in by crane.
• Trees. Seattle protects many large trees. One near the building spot can move the footprint or require an arborist report.
None of these are hidden. We check all five on the first site visit, before you pay for design.
How long does a Seattle ADU permit take?
Longer than most people expect, and it's getting slower. We went through the City of Seattle's own permit records for every new DADU permit issued since 2024, leaving out permits bundled with a new main house:
• 2024: a typical permit took about 5 months from application to approval
• 2025: about 5 and a half months
• 2026 so far: about 6 and a half months
You may have read that pre-approved plans get permits in weeks. The city's pre-approved DADU plans do skip much of the design review, but your site still gets its own review for slopes, trees and drainage.
A typical full timeline:
1. Site visit and feasibility: a week or two
2. Design and engineering: about 2 to 3 months
3. City permit: about 5 to 7 months
4. Construction: about 5 to 7 months
Source: Seattle Open Data, Building Permits, November 2026.
Why do ADU quotes differ so much?
Two quotes for the same ADU can be far apart because they rarely cover the same work. Before comparing totals, line them up on these points:
• Is it turnkey? Some prices leave out design, permits, utility hookups or fees. Ask for a written list of what's excluded.
• Allowances. A low quote often hides cheap allowances for cabinets, fixtures and flooring that you'll upgrade later at your own cost.
• Site work. Excavation, sewer, foundation and drainage should be priced for your lot, not a generic one.
• License. Check any contractor on Washington L&I's Verify a Contractor tool before you sign.
• Payment schedule. Payments should follow finished work, not run ahead of it.
Frequently asked questions
How much does a backyard cottage cost in Seattle in 2026?
Most land between the mid $100,000s for a small studio and the high $300,000s for a full two-bedroom, turnkey, on a normal lot. The ADU planner gives a ballpark for your own project.
Is it cheaper to build an ADU in Bellevue or Seattle?
The building itself costs about the same in both. Bellevue lots tend to be bigger and flatter, which can save on site work and fit a larger unit.
Can I build a detached ADU in Bellevue?
Yes. Bellevue adopted new housing rules on June 24, 2025 that allow detached ADUs on residential lots. Before that, ADUs had to be inside or attached to the main house.
How big can a DADU be in Seattle?
Up to 1,000 square feet in Neighborhood Residential zones, not counting a garage. The lot must be at least 3,200 square feet.
Do I need to live on the property or add parking?
Not in Seattle. The city dropped the owner-occupancy and off-street parking requirements for ADUs in 2019. In Bellevue, ADUs under 1,000 square feet, or within half a mile of frequent transit, need no extra parking.
What is the cheapest way to build an ADU?
Keep it small, simple and close to the street sewer. Converting an existing garage or basement usually costs less than building new. Pre-approved city plans can save on design, but they don't change the cost of the lot work.
Get a price for your lot
The fastest way to a real number is the Genpro ADU planner: pick your size and finish level and get a ballpark in about two minutes. When you're ready, call us at (253) 293-9402 or send us your address. We'll tell you what your lot allows before you spend anything on design.